Summary
A $21.6 million NHDOT rebuild of Rt. 101 is fully funded and on track: new roundabout at Swanzey Factory Road, replacement of the 1933 Branch River bridge, 5-foot shoulders, and a left-turn lane at Branch Road. Construction runs spring 2029 to fall 2031, with a public hearing May 28.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 27, 2026.
Impact analysis
Road and bridge work costs taxpayers nothing locally, but the City will pay for the water line replacement through its CIP.
All travelers on Rt. 101 — better pavement, safer intersection, bikers and pedestrians get real shoulders.
About 34 properties along the corridor will have right-of-way impacts; several Marlboro Road homes face retaining walls.