Eversource Transmission Structure Replacement Access
Keene
Summary
Eversource needs to cross city-owned land in Swanzey to reach transmission lines near the airport. The city is switching from an easement to a revocable license to keep more control.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 22, 2026.
Impact analysis
No direct city cost; Eversource bears restoration expenses.
Eversource and reliable electric transmission service for the region.
None identified; invasive species and stone wall concerns were addressed through state review and an agreement.
Mentions & discussions (2)
Municipal Services, Facilities and Infrastructure Committee - Jul 22, 2026
Eversource needs to replace five aging wooden transmission towers and wants temporary access over Old Gilsum Road for up to a year, including breaching a stone wall on the city boundary, with restoration promised.
Municipal Services, Facilities and Infrastructure Committee - Mar 25, 2026
Eversource needs to cross city-owned land in Swanzey to reach transmission lines near the airport. The city is switching from an easement to a revocable license to keep more control.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Keene
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.